Western Wake Freeway
Overview
New location roadway from NC 55 at SR1172 (Old Smithfield Road) to NC 55 near SR1630 (Alston Avenue) in Wake County.
Length
Approximately 12.6 miles
Estimated Cost
Preliminary cost is estimated at $783.7 million. Final costs will be determined during design.
Timeline
| Financial feasibility study | Complete |
| FEIS Reevaluation Report | Complete1 |
| Award construction contract | September 2008 |
| Open to traffic | 2011 |