Monroe Connector/Bypass

Overview

Preferred Alternative
Monroe Connector/Bypass
Click to Enlarge

Description
New location roadway from US 74 at I-485 in eastern Mecklenburg County to US 74 near the Town of Marshville in Union County.

Subsurface Drilling


Length
Approximately 19.7 miles

Estimated Cost
Preliminary cost is estimated at $750-$825 million. Final costs will be determined during design.

Free alternate route
Existing US 74.

Timeline

Completed Draft Environmental Impact Statement
May 2010 Final Environmental Impact Statement
2nd Quarter 2010 Record of Decision
Late 2014 Project Open to Traffic